MAGNOLIA — The town of Magnolia discussed updates and funding for several key infrastructure projects during its Feb. 24 meeting, including the Magnolia Sun Valley Sewer Improvements Project and the 2022 Well Generator Project.
The Sun Valley sewer project received $525,000 through the Community Development Block Grant (CDBG) program to cover cost overruns caused by high demand in the construction market and limited contractor availability. The funding will support a new sewer pump station, approximately 1,650 feet of gravity sewer lines and 14 manholes.
Joe McKemey with McDavid Associates explained that the funds will be drawn from the 2021 CDBG allocation, requiring certain portions of the scope of the work previously included in the 2022 grant to be moved to the older grant first. The amendment does not affect the existing $1,488,700 already allocated for the project. The town has committed $3,000 in local funds to support the work.
“The additional funds will partially fund the new sewer pump station in Forest Lane,” he explained.
The need for the project stems from improperly installed sewer lines in Sun Valley and Bobby Baker Lane, which were constructed years ago. Many lines are shallow, not properly graded, and contain too few manholes, causing frequent backups.
“We went out there one day, and we saw the sewer line in some places five, six inches deep,” said McKemey. “The pipes are laid so shallow and not at the proper grade, that they back up, and they have to go out there, and they have to get a plumber to clean out the lines. And it’s a liability because ultimately, if anybody were to ever make a stink about it, it’s ultimately the town’s responsibility because of the way the government’s going to look at it.”
The new infrastructure will correct these deficiencies, including a pump station designed to serve current homes and potential future development. The project also includes a short force main connecting to an existing manhole.
“There will be a new force plant that comes from this pump station that’s only about 400 feet long, and it will discharge into a manhole that’s there at the intersection,” said McKemey.
Public comment was solicited but none was offered. For the next public hearing the board discussed the 2022 Well Generator Project.
The town completed the installation of a new generator at Well Number 2, funded by an American Rescue Plan Act (ARPA) grant. The generator features an automatic transfer switch, ensuring seamless operation during power outages, and can run nearly 48 hours without refueling. The project budget was adjusted to reflect final costs, including minor reductions in engineering and advertising expenses, with remaining funds transferred back to the town’s waterline project.
McKemey noted that the new generator provides critical support to the town’s water treatment plant and elevated storage tanks, maintaining water pressure during storms or utility interruptions. “That project, the overall construction was $122,470,” he explained.
“That generator is strong enough to run the well and run the treatment plant. If you have a storm and the generators are full of fuel and the generators work properly, then, yes, your system should be self-sustaining. And as long as they can keep that elevated storage tank full of water, you will have pressure,” he added.
Board members also discussed ongoing waterline construction along Main Street, noting the contractor is navigating challenges with existing utilities, trees, and limited space, but progress has been smooth, with completion expected by early September.
“It’ll be tough for him in some places,” explained McKemey. “People just need to be aware, and they need to be, we’ll be trying to be a little bit forgiving.”
Twitter
Facebook
Instagram



